• K-12 School building 16,218 SF of Asbestos containing roof removal (night work)

    • 5000 SF of removal per night in conjunction with GC for next day dry-in

  • 32,000 SF of ACM mastic / carpet removal

  • 40, 251 SF of Non-ACM flooring removal

  • Project Duration: 51 Days

  • College Dorms

  • 7 building apartment complex purchased by College

  • 36 units per building (252 total)

  • 50-70% removal of each unit

  • Project Duration: 45 days

  • A North Texas City Hall

  • Asbestos Abatement and Mold Remediation of 6 Floors

    • Asbestos Removal of all drywall and carpet / mastic throughout entire building

    • Mold Structural Remediation of all remaining building materials post asbestos abatement.

  • Fully prepped and ready for remodel

  • Project Duration: 124 Days

  • A Florida Coast Beach front hotel

  • 181 Rooms / 6 Corridors / Break Room / Office Spaces

    • Content manipulation and protection for every unit

    • Roughly 30-40% room demolition

    • Duct Cleaning

  • Project Duration: 45 Days